Heat pumps

Do you need to upgrade your electricity supply for a heat pump?

Often not: many homes can take an air source heat pump with no upgrade to the incoming electricity supply. It depends on your main fuse, the other big electrical loads in your home and whether you share a supply cable with a neighbour. Your installer should check this at the survey, and your local network operator must be told about the heat pump either way.

12 min read • Last reviewed • England & Wales

The short version

  • Household main fuses typically range from 60A to 100A, and heat pumps typically demand between 16A and 32A, so many homes have room. The real test is the maximum demand of the whole home.
  • The installer checks the main fuse, consumer unit, earthing and bonding, cable route and other big loads.
  • A looped supply (one cable shared with a neighbour) is the usual complication. It means applying to the network operator before connecting, and may mean new cabling and groundworks.
  • Your Distribution Network Operator (DNO) must be told every time, either within 28 days after installation or by application before connection.
  • Standard unlooping is not normally charged to the customer. A move to three phase is.

A supply issue found late can hold up a job, so it is worth knowing what is involved. For how this fits into the whole visit, see what happens in a heat pump survey.

Why many homes need no upgrade, and when they do

Your home’s supply ends at the cut-out, the sealed unit that houses the main fuse. A government-commissioned report on looped connections says that fuse typically ranges from 60A to 100A, while heat pumps typically demand between 16A and 32A depending on the home’s heating needs. It adds that in operation a heat pump “is almost never going to draw the full power”.

So the question is what else runs at the same time. The same report puts an electric shower at 7–10kW and a single-phase EV charger at up to 32A (7kW). Add those to a heat pump and a 60A fuse starts to look tight. SP Electricity North West, the network operator for the North West of England, says heat pumps can use as much electricity as a domestic power shower “but for much longer”.

That is why the installer works out your maximum demand: the national connection form requires a load survey of the whole home plus the new equipment. You are more likely to need work if demand comes close to your fuse rating, the supply is looped, the equipment at the meter has a safety problem, or the heat pump is large. See also how much electricity does a heat pump use?

An electricity meter and consumer unit in an under-stairs cupboard of an older English house, with grey cables clipped to the wall
A survey checks the supply at the meter and consumer unit before a heat pump is added to the load. Illustrative image.

What is checked on your electrics

MCS’s design standard, MIS 3005-D, says the installer must make sure the electricity supply is adequate for the size of heat pump specified. For new electrical work, Approved Document P says the existing installation should be checked so that existing equipment, including the distributor’s, can carry the extra load, adequate protective measures are used, and earthing and bonding are satisfactory. In practice, expect these checks:

What is checkedWhat they are looking for
Main fuse (cut-out) ratingThe rating sets the limit. If it is unknown, the DNO can confirm it, and a photo can be sent with the form.
Maximum demandA load survey of the whole home plus the heat pump.
Consumer unit and spare wayWhether there is space for the new circuit, or whether a separate or replacement unit is needed.
Earthing and bondingWhether the arrangements are satisfactory before new work is added.
RCD and circuit protectionWhat protection the new circuit needs, which the electrician decides under BS 7671, the UK wiring standard.
Cable runThe route and size of the cable from the consumer unit to the outdoor unit.
Other big loadsEV chargers, batteries, solar, electric heating, electric showers and similar.
Looped supply and meter detailsSigns of a shared cable, the meter type and the MPAN (your supply number).

Do not open the cut-out yourself: the form says it must not be opened unless authorised. Approved Document P says the existing wiring only has to be upgraded if the new work affects its safety or cannot be operated safely because of its condition, so ask your electrician what must change and what is merely advisable. If you have or plan solar panels, a battery or an EV charger, mention them at the survey.

What if you have a looped supply?

A looped service is where two or more properties share a single service cable from the main network. The cable enters the first house, then a second cable runs from that meter position to the next. SSEN says this is no longer installed today but is still found in many older terraced and semi-detached homes, and the government report estimates that 11–17% of homes in Great Britain may be affected. If you live in one, see also our guides to terraced houses and semi-detached houses.

A looped service is safe to use, National Grid says, but may need to be removed if you or your neighbour need more power, for example for a heat pump. A common sign is two cables entering the bottom of the cut-out, below the fuse, rather than one. It is not always visible, so the operator may need a photo or a visit.

Unlooping means running a new cable from the main network. It normally involves digging, often on a driveway, and your neighbour has to be involved. The operator reinstates the surface and discusses the work with you both first. The government report says several operators may fit a load limiter as a short-term measure until unlooping can be scheduled, though this is more likely for EV chargers, and other operators do not use them.

Watch the timing. One operator told the government’s researchers unlooping takes 3–12 weeks where there are no complications, and up to 6 months to a year or longer if there are issues such as a neighbour dispute. Under the scheme regulations, an air source heat pump voucher from the Boiler Upgrade Scheme expires three months after it is issued. That is not a rule linking the two, but if your supply is looped it makes sense to raise it with your installer early, ideally before the grant is applied for.

Single phase or three phase?

Most homes have a single-phase supply. SP Electricity North West describes a standard domestic supply as single phase, and the government report calls three-phase homes rare. The operator’s standard three-phase connection offers 80 amps per phase.

The threshold that matters for most heat pumps is 32A. That is the limit for the simpler notification route, and SP Electricity North West expresses it as 7.36kW of AC electrical input. This is the power the heat pump draws, not the heat output quoted in its name, so a heat pump’s rated size is not a direct guide. The installer should check the figure for the specific model, and heat pump sizing matters here. SP Electricity North West says an upgrade to three phase comes in where a single-phase supply rated between 60 and 100A would need more than 100A after the demand calculations.

Connect and notify or apply to connect?

MIS 3005-D says the installer must make sure the installation is notified to the DNO under the procedures published by the Energy Networks Association (ENA), with permission sought in advance where necessary. Both routes use the same national form.

Connect and notify means the installer can connect the heat pump, then notify the DNO within 28 days of installation. On the form, all of these must be true:

  • Only one additional piece of equipment is being connected.
  • The cut-out rating is known, there are no safety concerns or other issues with the DNO’s equipment, and the supply is metered.
  • It is not a looped service.
  • Maximum demand is below the cut-out rating and, on ordinary whole-current metering, below 13.8kVA per phase (60A) unless the load is limited to below the fuse rating.
  • The heat pump system is under a single controller, with a maximum demand of 32A or less.
  • The model is marked “Connect and Notify” in the ENA’s heat pump database.

Apply to connect applies if any of those fail. The application must go in before the equipment is connected, and the installation may only take place after DNO approval. Where maximum demand is above 60A and up to 100A, the DNO should assess the supply capacity and confirm within 10 working days of receiving the completed form. Above 100A, different timescales apply. Installing an EV charger at the same time as a heat pump also fails the one-device test, so it needs an application.

Who submits it? Normally the installer, and MCS puts the duty on them, though the Energy Saving Trust notes the homeowner can do it too. To find your DNO, use the first two digits of the MPAN on your bill. For example, SP Electricity North West covers the North West of England, SP Energy Networks covers Merseyside and North Wales, and National Grid covers the Midlands, South West and South Wales.

Who pays for a supply upgrade?

It depends on the work, and it is the network operator’s charge rather than the installer’s.

WorkWho usually pays
Standard unloopingUsually not you. The government report says all DNOs state the customer does not pay and the cost is spread across bill payers. SSEN says this depends on eligibility criteria, such as a typical household supply of up to 100A per phase.
Extra work during unlooping (such as moving the meter)You may have to pay.
Main fuse, cut-out or service cable upgradeOften the DNO, but ask your network operator before you rely on it. Ofgem said in 2021 that DNOs funding this was in consumers’ interests, for fuses up to that operator’s standard size at single premises fused at 100A or less per phase.
Network reinforcementUsually not you, but check. Since April 2023 network operators have funded reinforcement for most customers taking power from the network. SP Electricity North West’s charging statement says it fully funds it for an existing home that stays on a service fused at 100A or less per phase with ordinary metering, subject to conditions. The national form still warns it may be charged to you, and the operator says larger heat pumps may need an upgrade that could incur a cost.
Single phase to three phaseYou. The government report says the consumer is responsible for this cost.

Policies can change. SP Electricity North West’s Lancaster trial page says unlooping is currently done at no charge “but this could change in future”, and Ofgem accepted in 2021 that it might not be able to enforce its view on fuse and cut-out funding, so ask your operator what applies to you now. The cost of any chargeable network work depends on your property, and the network operator quotes it.

Work inside your home, such as a new circuit or consumer unit, is separate and part of the installer’s quote. Installers on MCS’s redeveloped MCS:2025 scheme commit to telling you about additional work and its cost at the quotation stage. MCS is moving installers to that scheme in phases, so if yours is not yet on it, ask for the same thing. The total depends on your property: the system size, any radiator or pipework changes, the outdoor unit position and pipe run, hot water and electrical work. See heat pump costs in Manchester and how to compare heat pump quotes.

Part P and your electrical certificates

Part P is the electrical safety part of the Building Regulations. In England, Approved Document P makes a new circuit or a replacement consumer unit notifiable, and a heat pump normally has its own circuit. The Welsh edition likewise lists new circuits back to the consumer unit as notifiable.

In England the work must be certified in one of three ways: by a registered competent person who self-certifies, by a registered third-party certifier, or by a building control body. The Welsh edition sets out two routes: a registered competent person or a building control body. A registered installer should give you a BS 7671 electrical installation certificate, and the occupier should receive a Building Regulations compliance certificate.

Keep both with your heat pump paperwork. GOV.UK says a competent person certificate shows up in solicitors’ searches when you sell. Your installer may use a separate electrician, as long as you know who certifies the work.

What to ask, and where ByEco stands

Before you sign, ask any installer:

  • What is my main fuse rating and calculated maximum demand with the heat pump?
  • Is my supply looped, and how do you know?
  • Is this model connect and notify, and who sends the form?
  • Is any work needed from the network operator, and who pays for it?
  • Who will certify the electrical work?

We are MCS certified for air source heat pump installation (certificate IAA10330), and we apply for the £7,500 Boiler Upgrade Scheme grant on your behalf, where you may be eligible. Get in touch for a free survey: we will check your electrics alongside the rest of your home, explain anything the network operator needs to do and give you an itemised quote. If you are happy with it, we go ahead. See our air source heat pump service, read about grants and rebates or book a free survey.

Sources

Every figure on this page was checked against primary sources on 31 October 2026. Grant rules, planning rules and prices change — if you are reading this much later, verify before acting.

Book your free home survey

Every home is different. The cost depends on the size of system, any radiators that need upgrading, the pipework and where the outdoor unit goes. Get in touch and we will arrange a free survey of your home and give you a clear quote. If you are happy with it, we can go ahead.

Common questions

Do I need a new fuse for a heat pump?

Not always. Household main fuses typically range from 60A to 100A, and heat pumps typically demand between 16A and 32A. Whether yours is enough depends on the maximum demand of the whole home, including showers, EV chargers and other big loads. Your installer works this out, and any change to the main fuse is arranged through the network operator.

Does my network operator need to know about my heat pump?

Yes. Your Distribution Network Operator must be told about every heat pump, and MCS requires the installer to make sure this happens. If the installation meets every notification criterion, the installer connects it and notifies the operator within 28 days. If not, an application goes in before connection, and the work may only go ahead after approval.

Can I have a heat pump on a looped supply?

Possibly, but it needs more steps. A looped service fails the notification criteria, so an application must go to the network operator before connection. The operator may need to replace the shared cable with a direct one, which usually means groundworks and involving your neighbour. Several operators can use a temporary load limiter in some cases. Raise it early, as unlooping can take weeks or months.

Who pays to unloop an electricity supply?

Normally not you, for standard unlooping. A government-commissioned report says all network operators state the customer does not pay for standard unlooping, because the cost is spread across electricity bills. You may have to pay for extra work done at the same time, such as moving the meter or upgrading to three phase. Confirm the position with your operator, as policies can change.

Do I need three phase power for a heat pump?

Usually not. Homes commonly have a single-phase supply, and the simpler notification route covers a heat pump system with a maximum demand of up to 32A. Three phase becomes relevant if the demand calculation for the whole home goes beyond what a single-phase supply can provide. It is a chargeable service from the network operator, so ask your installer whether the design can avoid it.

Is heat pump electrical work notifiable under Part P?

Usually, yes. In England, installing a new circuit is notifiable under Part P of the Building Regulations, and the Welsh Approved Document also lists new circuits back to the consumer unit. In England the work must be certified by a registered competent person, a registered third-party certifier or a building control body; in Wales, by a registered competent person or a building control body. Ask for your electrical installation certificate and Building Regulations compliance certificate.

More advice